05 - Category Rooms Allocation Report – CARAR
PAD Location: Synergy SIS>Mass Scheduling>Schedule Control>Master 
 Builder Option Set
The purpose of the Category Rooms Allocation Report is to identify 
 allocations and scheduling issues related to rooms. The report lists each 
 subject category and the rooms assigned to them.
This report can help identify areas where a shortage of rooms is causing 
 scheduling problems. Key numbers to look at are Requested Percentage and 
 Scheduled Percentage. If Requested Percentage is less than 100%, it generally 
 indicates the rooms are shared with other subject categories. If Scheduled 
 Percentage is less than 100%, it indicates that some courses in the category 
 were scheduled without rooms.  